Uttarkashi, Uttarakhand:
In a major breakthrough in rescue ops, a thick iron mesh which came in the way of the auger machine drilling through the rubble at Silkyara tunnel to create an escape passage for the trapped workers has finally been removed, officials said today.
Former advisor to the Prime Minister’s Office Bhaskar Khulbe said it would take 12 to 14 hours more to complete the drilling and reach the trapped workers.
“The problem which was created due to the iron mesh has now been solved. The mesh has been cut by the use of the iron cutters,” Mr Khulbe said.
“It will take 12 to 14 hours more to complete the drilling and reach the workers. After that, it will take three more hours to take the workers out one by one and that will be done with the help of the NDRF,” he added.
According to Mr Khulbe, it took about six hours to cut the iron mesh.
The drilling of 800 mm diameter steel pipes through the rubble had to be halted for some hours after hitting the hurdle late Wednesday.
With the hurdle removed, the process of pipe pushing has resumed, officials said.
Meanwhile, all arrangements have been made to provide immediate medical care to the 41 trapped workers after they are evacuated, officials said.
A 41-bed separate ward has been readied at the Community Health Centre in Chinyalisaur for Silkyara tunnel evacuees and 41 ambulances wait outside the tunnel to rush them there as soon as they crawl out, officials said.
(Except for the headline, this story has not been edited by NDTV staff and is published from a syndicated feed.)