Palnadu Water Grid row: Notices to Telangana engineers raise questions over government’s response

Notices to Nagarjuna Sagar engineers over Andhra Pradesh’s Palnadu Water Grid project have triggered resentment and raised questions about Telangana’s response. Officials point to conflicting statements by two ministers and the delay in formally approaching the KRMB.

Updated On – 20 November 2026, 12:38 PM

Palnadu Water Grid row: Notices to Telangana engineers raise questions over government’s response

Hyderabad: The Congress government’s move to hold the Nagarjuna Sagar engineers responsible for failing to flag Andhra Pradesh’s Palnadu Water Grid project has raised questions over its own response, particularly as the government claims it was already aware of the project.

The Irrigation Department sought explanations from engineers at the Superintending Engineer, Executive Engineer, Deputy Executive Engineer and Assistant Engineer levels for allegedly failing to alert the government about the construction of three intake wells and related infrastructure. The government has also sought an explanation from the Nalgonda District Collector.


Sources said reports from the Collector and Nagarjuna Sagar Chief Engineer had been submitted to the administration. Though their contents could not be independently verified, action is likely against at least two officials. Irrigation engineers are reportedly opposed to any attempt to make their colleagues scapegoats.

“If the Minister says the government was already aware of the project and had taken it up with the Union Jal Shakti Ministry, the Krishna River Management Board (KRMB) and the Andhra Pradesh government, why are field-level officials now being held responsible for not reporting it?” an Irrigation Department engineer questioned.

The notices have caused resentment among officials, who feel they are being singled out despite the government’s claim of prior knowledge. They are considering a strong response if action is taken against their colleagues.

The conflicting statements by Irrigation Minister N Uttam Kumar Reddy and Roads and Buildings Minister Komatireddy Venkat Reddy have added to the questions. While Uttam said the government was aware of the project and had taken it up with the authorities concerned, Venkat Reddy said he had reprimanded officials for failing to bring it to the government’s notice.

The project’s timeline also raises questions. Andhra Pradesh floated tenders in January and issued a Government Order on August 4. Survey and mobilisation activities had reportedly begun in March. The Rs 1,200-crore project involves three intake wells on the right bank of Nagarjuna Sagar and 200 tanks to draw 1.86 TMC of water for drinking needs in Palnadu district. It is jointly funded by the Centre and Andhra Pradesh under the Jal Jeevan Mission 2.0.

Construction had reportedly reached 20 per cent before Telangana lodged a formal objection with the KRMB on November 16, seeking its intervention. But if the government had been tracking the project since its inception, the delay in formally approaching the river management board needs an explanation. If it learnt about the works only recently, the Minister’s claim of having already taken up the matter with multiple authorities requires clarification. Either way, the notices to engineers do not address the central issue of the government’s own response.

While the State government wrote a letter to the KRMB on November 16 reportedly opposing the Palnadu Water Grid project, the Congress government is unwilling to make public the contents of the letter.

Apparently, the project also was not included in earlier KRMB meeting agendas as Telangana had not formally raised the issue. The 21st full-fledged meeting, scheduled for October 26, has been postponed three times. If the government was aware of the project and opposed it, it could have raised the issue at earlier meetings or sought its inclusion in the agenda.

[]