Construction of the 3.39-km multi-level interchange at Gachibowli’s IIIT Junction has gained momentum after the monsoon. With 43 of 54 foundational pillars completed, the project aims to ease congestion and improve connectivity across Hyderabad’s IT corridor.
Published Date – 18 November 2026, 05:05 PM
Hyderabad: With the monsoon finally receding, the ground-level construction of the multi-level interchange at Gachibowli’s IIIT Junction has shifted into top gear, marking a decisive post-monsoon push to decongest Hyderabad’s bustling IT corridor.
Cyberabad Municipal Corporation (CMC) officials told ‘Telangana Today’ that of the 54 foundational pillars, the work on 43 pillars was complete, with heavy structural concrete beam installation underway for three interconnected steel flyover stretches at Gachibowli.
The CMC is building a 3.39-km signal-free network under the Hyderabad City and Innovative Transformative (H-CITI) project to eliminate one of the IT corridor’s worst traffic bottlenecks. The network comprises three elevated steel flyovers and a six-lane underpass.
The Level-1 Bi-Directional Flyover is a 720-metre, four-lane corridor to handle two-way traffic between ISB Road and DLF Road. Five edge pillars along the flyover are engineered to support Level-1 and Level-2 structures, allowing two curved upper-level flyovers — ISB Road to Gachibowli (1.20 km) and DLF Road to Lingampally (948 metres). The dual-level design reduces land acquisition and overall costs, officials said.
Level-2 Unidirectional Flyover (DLF to Lingampally) spans 948 metres and uses a shared double-decker pier system, with five dual-load edge pillars on the lower deck and dedicated landing pillars along the Serilingampally–Gachibowli Stadium stretch, easing movement toward Lingampally and Gachibowli Stadium.
Meanwhile, another Level-2 Unidirectional Flyover is a 1.2-km, three-lane elevated stretch for commuters from ISB Road towards Gachibowli and Indira Nagar. The longest of the three elevated structures at the junction, it follows a second-tier, or upper-deck, alignment and uses prefabricated structural steel girders. It is engineered to carry right-turning traffic over the lower Level-1 flyover without signal stops.
“The HCITI project, targeted for completion by May 2027, is expected to reduce peak-hour travel times by 10 to 15 minutes for nearly 4 to 5 lakh daily commuters between HITEC City, Financial District, Kokapet and Lingampally and would streamline access to DLF, ISB, Financial District and Outer Ring Road,” said CMC officials.